The National Company Appellate Tribunal (NCLT) in the case National Company Appellate Tribunal (NCLT), comprising of the bench of Justice M. Venugopal (Judicial Member) and the technical member, Shri Kanthi Narahari observed while adjudicating an appeal filed in Prashant Agarwal v Vikash Parasprampuria, has stayed in the Corporate Insolvency Resolution Process (CIRP) the constitution of […]

The National Company Appellate Tribunal (NCLT) in the case National Company Appellate Tribunal (NCLT), comprising of the bench of Justice M. Venugopal (Judicial Member) and the technical member, Shri Kanthi Narahari observed while adjudicating an appeal filed in Prashant Agarwal v Vikash Parasprampuria, has stayed in the Corporate Insolvency Resolution Process (CIRP) the constitution of the Committee of Creditors (COC) of Bombay Rayon Fashions Ltd. on 15.06.2022, the order was passed.

FACTS OF THE CASE:

The Operational Creditor or the Respondent, Vikash Parasprampuria is the sole Proprietor of Chiranjilal Yarn Traders and the respondent had supplied goods to a public listed company i.e., Bombay Rayon Fashions Limited (“Corporate Debtor”). The Operational Creditor raised nine invoices which was accepted by the Corporate Debtor without any demur and it was noted that the dispute, protest and part payments were also made towards certain invoices.

The reminder letter was sent by the Operational Creditor when the Corporate Debtor failed to release balance payments letters followed by a Demand Notice under Section 8 of the IBC dated 05.11.2020, which was delivered to the Corporate Debtor but no response was received from the Corporate Debtor.

MUMBAI NCLT PROCEEDINGS

An application under section 9 of the Insolvency & Bankruptcy Code, 2016 was filled by the Operational Creditor before the NCLT Mumbai Bench, seeking to initiation of CIRP against the Corporate Debtor, for defaulting in payment of Rs.1,60,87,838/-, wherein the principal amount was Rs. 97,87,220/- and remaining was interest. 01.11.2020, was the default date.

the Operational Creditor placed reliance so as to justify the compliance of Rs. 1 Crore threshold for initiating CIRP of the NCLT judgement in the case Pavan Enterprises v. Gammon India, it was held in the case that interest is payable to the Operational of Financial Creditor then the debt will include interest, in terms of any agreement. However, by including the interest component the threshold of Rs. 1 Crore was being me and no reply has been filled by the Corporate Debtor.

NCLT DECISION:

An order dated 07.06.2022, the NCLT Mumbai Bench observed that the Corporate Debtor had time and again by its letter, invoices and by making part payment acknowledged its liability.

It was stated by the bench that the application under Section 9 was complete in all respects as required by law and there was a default in the payment of debt amount by the Corporate Debtor. The bench accepted the application and the CIRP was initiated against the Corporate Debtor, Mr. Santanu T Ray, Interim Resolution Professional was appointed.

NCLT PROCEEDINGS:

An application was filled by the appellant, Prashant Agarwal before the NCLT against the order dated 07.06.2022.

The settlement was proposed by the Respondent by submitting that if it would be satisfied if the Appellant pays the principal amount along with the CIRP cost towards settlement and on the settlement proposal, the appellant is yet to seek instructions.

Accordingly, the bench in the CIRP of the Corporate Debtor stayed the constitution of CoC and the CIRP process would otherwise continue.

The Appellant to accept or reject the settlement proposal of the Respondent, the bench listed the matter on 07.07.2022.